National highways execution to decline to 31 km/day during FY25: CareEdge Ratings

Tuesday 30th Apr 2024    15
National highways execution to decline to 31 km/day during FY25: CareEdge Ratings
 

According to CareEdge Ratings, the pace of construction is estimated to slow down by 7-10% in FY25 due to heightened execution challenges. The pace of construction for national highways in India during FY24 registered a healthy uptick of 20% to 34 km/day (PY: 28 Km/day).

However, despite the uptick, the pace of construction fared lower than 37 km per day reported in FY21 due to execution woes and increasing competitive landscape.

Furthermore, increasing project complexities, rising participation of moderate creditworthy sponsors and significant delay in the receipt of appointed date post award of the project are expected to pull down the execution pace by 7-10% during FY25 to around 31 Km/day. CareEdge Ratings expects national highways construction to slow down from 12,350 Km in FY24 to 11,100-11,500 km in FY25.

BOT-HAM remained the preferred mode of award constituting around 55% of the total projects awarded during FY21-FY24. CareEdge Ratings has observed significant delays in the execution of such HAM projects. Of the overall sample of HAM projects awarded after March 2020 amounting to Rs 1.50 lakh crore, approximately one-third of the projects with an aggregate Bid Project Cost (BPC) value of Rs 50,000 crore are facing delays ranging from 4-6 months beyond the grace period of three months. These projects have applied or received an extension of time (EOT) of a similar or longer period. Notably, another significant portion of NH-HAM projects with an aggregate BPC value of ~Rs.40,000 crore as of April 1, 2024 are still awaiting issuance of Appointed Date for more than a year as compared to Rs 14,500 crore as of June 30, 2023. Of the total awards of ~12,300 Km by National Highways Authority of India (NHAI) in FY22 and FY23, 20% continue to await appointed date for more than one year.

With the announcement of greenfield expressways and highways, the challenges towards land acquisition have aggravated, thereby elongating the receipt of the appointed date. Also, the permissible execution span for projects is uniform at two years, irrespective of the project scope i.e. brownfield/ greenfield expressway/ structurally complex, which has further contributed to the project delays. All the above factors have increased the project completion cycle from earlier 2.75-3.25 years to around 3.50-4 years presently, resulting in a higher turnaround time for project execution and a subdued execution pace in the sector.

CareEdge Ratings expects a (i) shift in awarding preference from EPC to Hybrid Annuity Model (HAM) and Toll projects in the medium term, (ii) a significant reduction in the share of EPC projects to around 25-30% in awards going forward. This shall also help in reducing the funding requirement for NHAI while focusing on the quality of construction.

“CareEdge Ratings expects a decline in the pace of construction of National Highways by 7-10% in FY25 as compared to FY24 to around 31 km per day. National Highways construction pace is expected to slow down from 12,350 Km in FY24 to 11,100-11,500 Km in FY25. The rising competitive landscape, escalating execution challenges, increasing project complexities, rising participation of moderate sponsors and elongation in receipt of appointed date from award are key challenges faced by the roads sector. NH- Hybrid Annuity Model (HAM) projects with aggregate length of over 2,200 km are yet to commence construction for over one year post award. All the above factors have stretched the project completion cycle from earlier 2.75-3.25 years to around 3.50-4 years. Notwithstanding the healthy order book of road developers, these factors are likely to result in a subdued pace of road construction for NHAI,” said Maulesh Desai, director, CareEdge Ratings.

“As project complexities rise and timelines elongate, it is imperative to swiftly address bottlenecks thus ensuring seamless infrastructure development. Going forward, CareEdge Ratings estimates a significant reduction in the share of EPC projects from around 50% to 25-30% due to awarding through revised toll concessions. This shall also help in reducing the funding requirements of NHAI while focusing on the quality of construction. Under revised toll concessions funding requirement for NHAI shall reduce to 20%-32.5% of project cost as against 100% for EPC projects. At the same time, peak debt requirement is likely to be lower by 10% vi-a-vis old BOT-Toll concessions due to equity support from NHAI,” he added.

 
 
 
To List or Submit your listings related to Logistics Directory - Click Here
 
 
 
Indian Logistics Info :: Facebook Indian Logistics Info :: Twitter Instagram Indian Logistics Info :: LinkedIn
© 2007 - IndianLogisticsInfo.com. All Rights Reserved
hit counter
Home  |  Overview  |  Advertise  |  Link to us  |  About us  |  Contact us  |  Sitemap  |  Privacy Statement